Kings Corridor data center applications (Forest Lane, Simms Farm, Sisson North, Sisson South)

Real Estate Pursuits 2 LC (applicant/owner for all four, per county page)

Status
Under review; Planning Commission public hearing set for Nov 18, 2026 (postponed from Oct 14)
Developer / parties
Real Estate Pursuits 2 LC (applicant/owner for all four, per county page)
Location
George Washington District (Route 3 / Kings Highway), Stafford County
Size
County page: four applications on 1,404.82 acres, about 10.5 million sq ft of data centers in 37 buildings and 14 substations (Forest Lane 26 buildings/8 substations on 844.92 acres; Simms Farm 1 building/2 substations; Sisson South 10 buildings/1 substation; Sisson North is substation-only). WJLA described the proposal as over 1,500 acres
Concerns / impacts
WJLA interviewed residents whose homes adjoin all four sites and who said they oppose the plan (WJLA). The county page lists no benefit figures
Last verified
2026-11-02

Milestones

Figures are attributed in parentheses to the outlet or company that reported them. Where sources disagree, we show both.

  1. Applications deemed complete between Mar 26 and Jun 27, 2025
  2. staff reported to recommend denial of most of the applications (WJLA, Oct 2026)
  3. Oct 14 2026 Planning Commission meeting canceled and the hearing moved to Nov 18, 2026 6:00 p.m. in the Board Chambers by agreement of the applicant and staff to allow further review and refinement (Stafford County)

Related records

2026-11-18
County planning Official record Stafford County · Kings Corridor data center applications (Forest Lane, Simms Farm, Sisson North, Sisson South)

Upcoming: Planning Commission public hearing, 6:00 p.m. in the Board Chambers, on the Forest Lane, Simms Farm, Sisson North and Sisson South data center applications (Stafford County).

Source: staffordcountyva.gov ↗

Sources

Found an error? Email support@virginiadatacenterwatch.com with a source link.