Data centers in Chesterfield County, Virginia

4 projects and 4 dated records · last verified 2026-11-02

Free weekly digest

Email digest: not open yet

The free weekly email digest is not accepting signups yet, and we collect no email addresses on this site. Everything on this site is free to read. Want it same-day? Neighbor, $4/mo.

Projects

Chesterfield County

Google Project Peanut (2100 Bermuda Hundred Road)

Google (per Richmond BizSense); county lists 'Peanut LLC'

Under construction; three buildings (county status July 2026)

Size: 300-plus acres; about 856,000 sq ft in buildings of about 285,000 sq ft each (filings per Richmond BizSense)

Last verified 2026-11-02 · 2 sources

Chesterfield County

Google Project Skye (4201 Moseley Road, Upper Magnolia Green)

Google (per Richmond BizSense)

Zoning approved (May 2025); first building expected 2027

Size: About 850 acres, four buildings planned (Richmond BizSense); county lists number of buildings as not specified

Last verified 2026-11-02 · 2 sources

Chesterfield County

Google Project Loch (750 Watkins Centre Parkway)

Google (per Richmond BizSense)

Zoning approved (May 2025); site work expected early 2027

Size: About 350 acres, three buildings planned (Richmond BizSense); county lists number of buildings as not specified

Last verified 2026-11-02 · 2 sources

Chesterfield County

Chirisa campuses at Meadowville Technology Park

Chirisa

Operational (existing buildings); more under construction

Size: County status table (July 2026): CTP-01 one existing building; CTP-02/03/04 two existing and one under construction; Digital Drive two buildings under construction

Last verified 2026-11-02 · 2 sources

Records & actions

2026-10-27
County planning Official record

County held a community data center forum at Brightpoint Community College's Chester campus; recording on the county's YouTube channel (county data centers page).

Source: chesterfield.gov ↗
2026-08-26
County planning News report

Deputy County Administrator Jesse Smith said at a press conference that the Board of Supervisors does not have an appetite for more data centers and staff would not recommend new applications; developers can still apply through the CUP process (Richmond BizSense, Aug 27, 2026). Not a formal Board vote.

Source: richmondbizsense.com ↗
2026-07-01
County planning Official record

County data center status table as of July 2026: Chirisa CTP-01 existing; CTP-02/03/04 two existing and one under construction; Chirisa Digital Drive two under construction; Peanut LLC (2100 Bermuda Hundred Rd) three buildings under construction; Upper Magnolia Green and Watkins Centre zoning approved; Old Bermuda Data Center (1931 Old Bermuda Hundred Rd) and Tradeport 95 (1250 Battery Brooke Pkwy) not approved, CUP required. Date shown is the first of July; the page says 'as of July 2026'.

Source: chesterfield.gov ↗
2026-04-09
DEQ air permit Official record

DEQ's list of issued air permits for data centers shows registration 52432-6 (Article 6 - mNSR) issued 2026-04-09 to Chirisa Richmond LLC in Chesterfield County. The list gives no project size or status; the entry says nothing about whether the facility is built.

Source: deq.virginia.gov ↗

Spot an error or a missing filing? Email support@virginiadatacenterwatch.com with the source link.